UNIT TITLE: PERFORM ESTIMATION AND COSTING FOR ELECTRICAL HOUSE WIRING
UNIT CODE: CONElM4018A2
UNIT DESCRIPTOR: This unit covers the knowledge, skills and attitudes required to perform estimation and costing for electrical house wiring. It includes preparing for works, drawing freehand sketches for electrical circuit, identifying side / place for electrical house wiring, estimating required materials for electrical house wiring works, human resources, labor cost and maintaining workplace, tools, equipment and materials.
NOMINAL HOURS: 50 Hours
LEARNING OUTCOME: At the end of this session, learners will be able to-
- Prepare for works.
- Draw freehand sketches for electrical circuit.
- Identify side / place for electrical house wiring.
- Estimate required materials for electrical house wiring works.
- Estimate human recourses.
- Estimate labor cost.
- Maintain workplace, tools, equipment and materials.
FACILITATOR NAME: Md. Jahangir Alam Tarafder ( Shamol )
TEACHER NAME: Shamim Ara Begum
Instructor
Jhalokathi Technical School and College, Jhalokathi.
-
If you have any query, please write.
-
The Structure of the course :
Only Online Course
Or
Blended Course
In addition to the online course . Physical demonstration is mandatory for this course , so i should go for Blended Course.
Lets go for 3 week of online course and 1 week of face to face training ( Blended Course ) .
Total Course : 21 days
Online Course : 2 Week
( 5 days per week for 1 hour )
( Saturday - Wednesday )
Face to Face : 1 Week
( 5 days daily 3 hours and
1 day final assessment for 5 hour )
-
If you have any query, please write.
-
-
-
If you have any query, please write.
-
-
Personal Protective Equipment, commonly referred to as "PPE", is equipment worn to minimize exposure to hazards that cause serious workplace injuries and illnesses. These injuries and illnesses may result from contact with chemical, radiological, physical, electrical, mechanical, or other workplace hazards. Personal Protective Equipment may include items such as below
- Apron
- Safety shoe
-
If you have any query, please write.
-
Electrical tools are tools used to work on an electrical system. These can include a wide range of tools such as below:
- Measuring tape
- "T square"
- Set square
- Drawing manual
-
If you have any query, please write.
-
Electrical Material is basically the parts or elements used in the making of any electrical construction project. These can include a wide range of materials such as below:
- Drawing paper
- Calculator
- Pen
- Pencil
- Eraser
- Paper
-
If you have any query, please write.
-
An electrical drawing is a type of technical drawing that shows information about power, lighting, and communication for an engineering or architectural project.
- Technical drawing
- Sketch
- Blue print
- Connection diagram
-
If you have any query, please write.
-
Electrical signs and symbols provide workers and others with information on electrical hazards and instructions on preventing harm. Labels, such as those used in PAT testing, inform people that electrical equipment and appliances are safe to use or not.
- Drawing symbols
- Connection symbol
- Load symbol
- Switch, socket, cut-out, sp, DP, MCB, MCCB, METER, Bus-Bar, earthing (grounding), changeover symbol.
- Main switch symbol
- Supply symbol
- Danger symbol
- Switch board symbol
- Conduit symbol
- Starter symbols
- Protective device symbol
- Motor symbol
-
If you have any query, please write.
-
Electrical Specifications means the specifications and requirements for electrical service to the Site.
- Product specifications
- Performance specifications
- Method specifications
- Specification manuals
-
If you have any query, please write.
-
- Personal Protective Equipment (PPE) is collected and worn as per job requirement.
- Workplace is prepared as per job requirement.
- Tools, equipment and materials are selected and collected as per job requirement.
-
- Drawing sheet / tracing paper papers are set on the job table as per drawing requirement.
- Freehand sketches are drawn through followed by customer requirement.
- Symbols are mentioned in the drawing papers as per requirement of the work.
- Details of sing & symbol are mentioned on index.
-
If you have any query, please write.
-
- House wiring place is identified and selected as per drawing.
- Selected side and identified point are shared to with the subordinate.
-
If you have any query, please write.
-
- Required area is measured and calculated as per drawing plan.
- Specification and volume of work is calculated by followed required specification.
- Appropriate formulas for calculating quantities of materials are applied.
- Material, fitting and fixture quantities are calculated as per drawing plan.
-
If you have any query, please write.
-
- Level of workers is identified according to work volume.
- Formulas for calculating require human are identified and calculated cost as per working days.
- Total work time is calculated as per working days.
-
If you have any query, please write.
-
- Work capacity of a man is calculated.
- Appropriate formulas for calculating require labor cost are identified and estimated as per working hour / days.
-
If you have any query, please write.
-
- Work area is cleaned in accordance with workplace procedures.
- Unused materials are stored for re-use or disposed following workplace procedures.
- Waste and scrap materials are disposed with following workplace procedures.
- Inventory of tools equipment are conducted and recorded as per checklist.
- Tools and equipment are cleaned and stored as per manufacturer's recommendation in appropriate location.
-